WIDENING & IMPROVEMENTS TO MYSORE BANTWAL ROAD (SH 88)
The State Highway (SH – 88) running between Mysore to Bantwal road was considered for widening and strengthening. The road runs through Mysore – Hunsur – Periyapatna – Kushalnagar – Suntikoppa – Madikere – Sulya & Puttur and intersects N.H. - 48 @ km. 14 from Bantwal. This road provides vital link between Mysore – Madikeri and Mangalore. All these districts attract tourists from India and Abroad. Mysore city is famous as a center of excellence in Education and Culture. Madikeri is a district Headquarters of Kodagu and is famous for scenic beauty and hill station. It is also rich in coffee plantation, orange groves and paddy fields. Mangalore district has important port cities, pilgrim places and major export center for coffee, timber, log and mineral with highest in industrialization potential. The Project Road carries sizeable volume of inter and infra State commercial traffic and tourist vehicles.
Total length of 220 km Road was divided into three packages for convenient implementation and faster completion.
PACKAGE – A FROM KUSHALNAGAR TO SAMPAJE :
Total length
:
from 1.64 km to 88.30 km
Agency Name
:
M/s. Nayak – Ashwini (JV)
Consultancy for DPR
:
M/s. India International Infrastructure Engineers Pvt. Ltd.
Supervision & QC Consultants
:
M/s. MSV Intl. Inc. USA Consultants
Contract Amount
:
Rs. 103.96 crore (Revised to Rs. 129.67 Crores)
Commencement Date
:
23rd May 2005
Period of completion
:
24 months
Scheduled completion date
:
December 2008
Status
:
Work under progress.
PACKAGE – B FROM KUSHALNAGAR TO SAMPAJE
Total length
:
from 88.30 km to 148.50 km
Agency Name
:
M/s. R.N. Nayak & Sons
Consultancy for DPR
:
M/s. India International Infrastructures Engineers Pvt. Ltd.
Supervision & QC Consultants
:
M/s. CES (I) Pvt. Ltd.,
Contract Amount
:
Rs. 103.00 crore
Commencement Date
:
25th October 2006
Period of completion
:
24 months
Scheduled completion date
:
April 2009
Status
:
Preliminary Works such as surveys completed. Erection of plant, pothole filling etc., under progress.
PACKAGE – C FROM KM 148.50 TO 220.40 KM (71.90 KM) SAMPAJI TO MANI:
The 1st call was issued vide Notification No. KRDCL/IFB/2007/43 dated 09.08.2007. The Board of KRDCL rejected the single bid received from M/s. R.M.N. - G.V.R (JV). This length of 71.90 km is ready for tender and the 2nd call will be invited through e-tendering process shortly.
 